Submittals are one of the hardest parts of a project engineer’s job, and not just for new PEs. Even senior project engineers with years of experience find them difficult: every project is different, requirements are spread across hundreds of pages of specs and drawings, and a single missed detail can turn into costly rework. If submittals feel confusing, you’re in good company.
Submittal review confirms that the product data, shop drawings, samples, warranties and other documentation proposed by the supplier and installer (typically a subcontractor) match the material requirements outlined in the project’s specifications and drawings before anything is ordered, fabricated or installed.
After receiving the submittal from the subcontractor, general contracting project engineers review it for compliance, and prepare a coversheet with any comments the design team should be aware of. This submittal package is uploaded back into the project management system (such as Procore or Autodesk) and then sent to the architect and engineers for formal review and approval.
Get it right and the submittal gets approved the first time, procurement moves, the work goes in once, and closeout is clean. Get it wrong and you find out in the field, where fixing it costs the most. Rework accounts for an average of 12% of project budgets, and details missed in submittal review are part of that potential cost.
The key issue is that project engineers, often early in their careers, are expected to catch every compliance gap on a tight review deadline, without tools built to help them do it quickly and thoroughly. So we put together this guide to lay it out as simply as possible: what you’re looking at, who’s responsible for what, a step-by-step checklist, a worked example, and how to write comments that get resolved the first time.
What Is a Submittal?
The specs and drawings spell out what needs to be built. A submittal is the subcontractor showing exactly what they plan to provide to meet those requirements: which product, which size, which finish, which connection detail. The most common submittal types are:
- Product data. Manufacturer cut sheets, spec sheets and performance data for off-the-shelf items like light fixtures, pumps or door hardware.
- Shop drawings. Drawings made by the sub or fabricator that show how something will be built and installed, like steel connections, ductwork layouts or curtain wall details.
- Samples. Physical pieces of a material, such as a tile, a carpet swatch or a paint drawdown, used to confirm color, texture and finish.
- Mockups. Built sections of the work, such as a piece of masonry wall, reviewed in place before full production.
- Closeout items. Warranties, O&M manuals and test reports, which the specs often list as submittals too.
The specs tell you which submittals each section needs. Look for the “Submittals” or “Action Submittals” article in Part 1 of each spec section, and check Division 01 for the general rules: format, number of copies, and how long the design team has to review.
How the Submittal Review Process Works
The exact flow varies by contract, but most jobs follow the same path:

- The specs set the requirements. The A/E writes them, and the GC lists every required submittal in the submittal register. The PE assigns each one to a sub and sets due dates working back from procurement lead times.
- The sub assembles the package. The sub gathers product data or draws shop drawings, marks which options it is providing, and sends the package to the GC with a transmittal.
- The GC does a first-pass review. This is your step. You check for completeness and coordination with other trades, and compare the product data against the specs and drawing schedules.
- The GC routes it to the A/E. You stamp it and send it up for technical review.
- The A/E reviews and stamps it. The architect and engineers check it against design intent and the contract documents.
- The response routes back down. It goes from the A/E to the GC to the sub, and everyone logs it.
- The sub orders or resubmits. If it comes back Approved or Approved as Noted, the sub addresses every note, verifies against the specs, then orders or fabricates. If it comes back Revise and Resubmit or Rejected, nothing gets ordered: the sub revises it and resubmits it as a new entry, and the loop starts again.
What the Review Stamps Mean
Wording differs by firm, but most stamps land in one of four buckets:

| Stamp | What it means | What happens next |
|---|---|---|
| Approved as Noted | Accepted, with comments that must be followed | Proceed and follow the comments. Usually no resubmittal; some firms require one |
| No Exceptions Taken | Complies as submitted. Often worded “Approved” or “Reviewed” | Proceed as submitted |
| Make Corrections Noted | Acceptable once the marked corrections are made | Proceed and make the corrections. No resubmittal needed |
| Revise and Resubmit | Real issues that need fixing first | Correct and resend for another review, tracked as Rev 1, 2, 3 |
Treat “Approved as Noted” as a to-do list. The notes are part of the approval, and they are easy to lose between the office and the field. Make sure they reach the sub, the foreman and whoever places the order.
Who Is Responsible for What
This part confuses a lot of people, including experienced reviewers. Under the widely used AIA A201 General Conditions, submittals are not contract documents. They show how the contractor plans to meet the contract documents. That means:
- The design team reviews for general conformance with design intent. It typically does not take responsibility for dimensions, quantities, or means and methods.
- The GC reviews before passing it on, coordinates between trades, and stays responsible for the work matching the contract.
- The sub stays responsible for the accuracy of what it submitted, even after approval.
In plain terms, an approval stamp does not move the risk of a mistake off the contractor. That’s why the GC’s review is worth doing carefully.
What this means is that even when an architect/engineer “approves” a submittal, they are only saying it appears to meet the project requirements, but if a submittal ends up not meeting project requirements set forth in the specifications or drawings, then the General Contractor and Subcontractors ultimately become responsible for absorbing the costs, schedule impacts, etc.
How to Review a Submittal: A 10-Point Checklist
Keep the spec section and the relevant drawings open side by side, and work through this list one item at a time. You don’t need to memorize it; that’s what the list is for.
- Right spec section, right item. Does the submittal match the spec section and the item it claims to cover?
- Every requirement is addressed. Go through the spec’s Part 2 (Products) line by line: manufacturer, model, size, rating, material, finish, certifications.
- Make sure there are not other requirements hidden in Part 1 or Part 3 of the specification.
- Options are clearly marked by the subcontractor. On cut sheets, the exact model and options should be highlighted and the others crossed out. If you can’t tell what’s being provided, neither can the architect. Reach out to the subcontractor to ask for clarification on the exact type, size, color, etc. for the product they submitted.
- The drawings agree. Check dimensions, quantities and locations against the plans, sections and schedules. A pump that meets the spec but won’t fit in the room is still a problem.
- Referenced standards are met. Specs often point to ASTM, UL or other standards. Check that the product data shows compliance. These are the little things that an inspector will catch during final inspections and fail the material, this is the biggest risk of rework that you don’t want to get yourself into.
- It works with the other trades. Look at connections, clearances, weights, power requirements and anything that touches another sub’s work.
- Substitutions are flagged. If something differs from the basis of design, it should be called out as a substitution and follow the spec’s substitution process, not slip through quietly.
- Deviations are listed. Ask subs to list any deviations on the cover sheet. It saves everyone time.
- Lead time fits the schedule. Note the lead time and check it against the install date.
A Worked Example
Here’s what that checklist looks like on a simple product data submittal. Say the spec for hydronic pumps calls for an in-line pump rated for 50 gpm at 40 feet of head, with a premium-efficiency 460V/3-phase motor and bronze fittings.
The mechanical sub submits a cut sheet. Working through the list, you find:
- The flow and head match, and the model number is highlighted. Good.
- The motor listed on the cut sheet is 208V. The electrical drawings show a 460V circuit for this pump.
- The fittings are listed as cast iron, not bronze.
- The pump’s footprint fits the mechanical room plan, but the drawings show a housekeeping pad that isn’t mentioned.
Each one is easy to miss on a cut sheet. In the field, each one becomes a real problem: a motor that can’t be connected, a material the engineer never approved, a pad nobody poured. That’s what the review is for: catching mismatches between the spec, the drawings and what’s actually being bought, before they reach the field.
How to Write Review Comments That Get Fixed
Vague comments create resubmittals. Specific comments get fixed on the first try. A good comment names the requirement, says what was submitted, and says what to do next:
“Spec 23 21 23, 2.2.B requires 460V/3-phase motor; submitted motor is 208V. Revise to 460V or submit as a substitution.”
A few habits help:
- Cite the spec section and paragraph, or the drawing number.
- One issue per requirement, so nothing gets missed.
- Separate what must change from what’s just a question, or comment.
- Keep it factual. The goal is a correct submittal, not a debate.
Common Mistakes
- Passing it through without reading it. The design team will catch some issues, but not coordination between trades.
- Reviewing against the specs only, or the drawings only. Many problems live in the gap between the two.
- Missing a later revision. Make sure you’re reviewing against the latest addenda, bulletins and ASIs.
- Using a submittal to ask a design question. If the documents are unclear, send an RFI first. Don’t make the design team answer a question buried in a shop drawing.
- Losing the notes. An “Approved as Noted” stamp that never reaches the field is the same as no review at all.
Tips That Make Reviews Easier
Most people learn submittal review on the job, and it takes practice at every level of experience. A few habits make it easier:
- Read the full spec section before you open the submittal.
- Keep a running list of what the design team catches that you missed, and why.
- Ask a senior PM or superintendent to walk you through one tricky review a week.
- Walk the site and look at installed work you reviewed. It connects the paper to the building.
Where Software Helps
The judgment in a review is yours. But much of the time goes to cross-referencing: finding the spec requirement, matching it to the right page of product data, checking the drawings. Remy compares submittals against specs and drawings, flags possible compliance issues and links each one to its source. It also includes training notes that explain why a requirement matters, so engineers at every level learn what to look for as they review. The engineer still makes the call.
The Short Version
- Read the spec before you open the submittal.
- Check against both the specs and the drawings.
- Write comments that cite the requirement and say what to fix.
- Treat “Approved as Noted” as a to-do list.
Frequently Asked Questions
What does a project engineer check in a submittal?
That the submitted product or shop drawing meets every requirement in the spec section, agrees with the drawings, coordinates with other trades, flags any substitutions or deviations, and fits the schedule.
What does “Approved as Noted” mean on a submittal?
The submittal is accepted with comments that must be followed. Usually no resubmittal is needed, though some firms require one, and the notes are part of the approval.
What’s the difference between a submittal and an RFI?
An RFI asks the design team a question about the documents. A submittal shows how the contractor will meet them. Resolve open questions with an RFI before submitting.
Does an approved submittal change the contract?
Generally no. Under common contract forms like AIA A201, submittals are not contract documents, and the contractor stays responsible for meeting the contract.